Blackout As Shiroro, Sapele Power Plants Shut

Nigeria’s electricity woes worsened as Shiroro Power Station in Niger State and Sapele II in Delta State were shut down, bringing the total number of plants not generating any megawatts of electricity to 10.

Shiroro, whose capacity was put at 600MW, was said to have seen its unit 411G1 tripped on emergency shutdown on the 86ES lockout relay; units 411G2 and 3 out for under water repair work; and unit 411G4 out on maintenance.

ALSO READ NASS To Send Full Details Of Budget To Buhari This Week

The Sapele II, built under the National Integrated Power Project, with its capacity put at 225MW, has four units. The GT1 was shut down for maintenance, GT3 out due to work by the Nigerian Gas Company at the gas station, while the GT2 and 4 units are out as a result of gas constraints.

Minister For works, power and housing Mr Babatunde Fashola
Minister For works, power and housing Mr Babatunde Fashola

Total national power generation stood at 2,774.2MW on Tuesday, down from 3,657.5MW on March 31. Generation from Egbin, the nation’s biggest power station, was limited to 415MW due to gas constraints, down from 1,085MW on March 15.

Shell’s Afam VI power plant generated the highest megawatts of electricity at 418MW as of 6am, the data showed.

The slide in power generation has worsened the blackout being experienced in many parts of the country as many consumers complained of outages lasting for hours on end.

Previous ArticleNext Article
Daniel Enisan is a content writer at edliner.com. With a degree in mass communication, Daniel is a full breed journalist. Daniel is a realist, loves the use of sarcasm, a movie and music junkie. He is also a poet and a good listener.

Leave a Reply

Your email address will not be published. Required fields are marked *